Project Cost Managment

                                                    Project Cost Formulas


 PV PLANNED VALUE
BAC * % PLANNED TO BE COMPLETED
 EV EARNED VALUE
BAC * % WORK COMPLETED
 AC ACTUAL COST
WORKED PREFORMED
 BAC BUDGET AT COMPLETITION
TOTAL BUDGET OF PROJECT
 CV COST VARIANCE
EV - AC
 SV SCHEDULE VARIENCE
EV - PV
 SPI SCHEDULE VARIENCE
EV/PV
 CPI COST PERFORMANCE INDEX
EV/AC
 EAC ESTIMATE AT COMPLETE
 BAC/CPI (CPI BASED FORCAST)
 ETC ESTIMATE TO COMPLETE
 EAC - AC
 VAC VARIANCE AT COMPLETE
 BAC - EAC
 TCPI TO COMPLETE PERFORMANCE INDEX
 BAC BASED (BAC - EV) / (BAC-AC)
 TCPI TO COMPLETE PERFORMANCE INDES
 EAC BASED (BAC - EV) / ( EAC-AC)



 

|Disaster Document| |Goals and Values| |Sample Mission Statement| |Customer Service Plan| |Employee Evaluation Form| |Sample Collocation Agreement| |Project Manager| |B-PON| |TDM TO IP TRANSITION| |Internet Links| |Network Operations Draft| |Information System Operations| |Project Cost Management| |PMBOC Knowledge Maping| |Home|